The Saw Mill Road Culvert Replacement Project is now complete, and the Township is moving forward with the final roadway improvements.
The contractor will be onsite tomorrow (Friday, September 11) to mill Saw Mill Road from Mortonville Road to Martingale Circle in preparation for paving. Milling is expected to be completed tomorrow, with paving anticipated to take place Monday or Tuesday (September 14-15), weather permitting.
Â
Â
One lane of Saw Mill Road will remain open to traffic at all times. Motorists should use caution when traveling through the work area and should expect traffic control measures and possible delays.
Â
The Township appreciates the patience and cooperation of residents and motorists as we complete the final phase of this important infrastructure project.
Â
Scott Swichar, Township Manager